ACCL have celebrated the completion of their largest project to date, which was as a part of the re-design and refurbishment of one of the most prestigious addresses in Canary Wharf for One of London’s leading Financial Powerhouses, MF Global. As a part of their restructuring exercise MF Global took the opportunity to set new Corporate Standards for their Network, the building already had an excellent Carbon rating which had to be maintained as part of the design process and installation, therefore one of the key considerations was to use contractors and suppliers who had exemplary environmental records.

 

Location:London

Challenges

Whilst ACCL were given sufficient planning and design time before the project commenced, the window for installation was extremely tight – less than three months, and even that got squeezed towards the end! “We spent a considerable amount of time beforehand perfecting the design with MF Global,” says Connors. “However, as with many projects the anticipated 18,000 ports grew to 22,000 and the timescales shrank.”

Design and installation considerations

To service each dealer desk, which has up to six computer systems on it, and the trading desks with up to eight outlets, ACCL designed a special housing to accommodate and manage the cabling requirements. It was important that the air flow around each of the desks was not compromised. So ACCL enhanced the design to include an underfloor air cooling system, ensuring that the installation of the Cat6 cable runs didn’t compromise the movement of the cool air. With significant numbers of power and infrastructure cable running under the floor, it was important to co-ordinate all these services to maximise the air flow and ensure an even temperature was maintained. Each desk cluster was fitted with a number of conduits, anchored back to a central location. The purpose of this was to identify exactly where each of the cables terminated in order to prevent masses of floor being taken up in the future just to find the cable end points.

 

One of the specifications for the infrastructure project was that it should allow for ease of movement with the ability to reconfigure the arrangements of the desks. This condition was tested very early on, when it was decided that the staff sitting on the second and third floors were going to swap places.

 

“As with any big re-organisation, there was a little bit of confusion whilst waiting on final seating plans to be confirmed,” says Connors. “The swap over was massive – 30 per cent in total. It certainly tested the flexibility of the infrastructure design, and I’m glad to say it performed exceedingly well.”

Further expansion

Now that the trading floors are up and running, MF Global is tackling the second phase of the project and extending the infrastructure from the dealing floors into the rest of the building including the deli area. “It’s all about keeping staff in the building connected,” says Connors. “So connectivity whilst at coffee is important.” MF Global made a decision early on to standardise on fixed networking points with plans to overlay a wireless network at a later date. To support this initiative 1,000 data points have already been installed in ceilings across the four floors.

 

Successful completion

Our outstanding Team here at ACCL worked closely with the MF Global Team to ensure that the project was brought in on time, to plan and within budget.

 

Watch our videos

About ACCL

ACCL designs, implements and supports the data and communications networks which provide connectivity and drive business performance. Privately owned, and with more than 25 years of experience in London and the South East, customers are at the heart of everything we do. Our specialist cabling services are designed with your current and future needs in mind, bringing high-quality solutions that are excellent value.

Our Other Case Studies

TUI

ACCL installs new 10 gigabit network with new fibre optic backbone to link twenty network cabinets at Tui’s Luton Head office

princesshay

ACCL install TAS solution for Princesshay Shopping Centre, creating a reliable and responsive communications system to increase the security and efficiency of the shopping centre.

logo-stdavid

ACCL improves the communications system at St David’s Shopping Centre

RAF Cable Installation

ACCL install state-of-the-art cabling infrastructure at RAF Museum in Hendon

Luton Hoo data cabling services

ACCL upgrades Voice and Data Communication network at Luton Hoo Hotel

Chelsea Gardens data cabling services

ACCL delivers a cabling upgrade to Chelsea Physic Garden

© Copyright Active Communication Company LTD | All Rights Reserved
  • Data Cabling
  • Data Cabling
  • Data Cabling
  • Data Cabling
  • Data Cabling
  • Data Cabling
Call Now Button